Saturday 25 August 2012

Walls

23 AUGUST 2012

Walls are getting constructed.








Tuesday 21 August 2012

Fallen fence

21 AUGUST 2012

Drove by the site after work and was dismayed to find that the temporary fencing has fallen!




Preparation for hebel walls

21 AUGUST 2012

Met with the fittings supplier this morning to confirm the positioning of our toilet accessories, before the plastering gets installed.

Happy to see that they are now preparing for the construction of the hebel wallsl




Roof completed

17 AUGUST 2012


Gutters & fascia installed

15 AUGUST 2012


Sunday 12 August 2012

Frame stage completed!

12 AUGUST 2012

The frame and window installations were completed on 10 August. We dropped by the site today to do a quick check and realised that one panel of windows were not double-glazed like the rest, the garage side door is a different size to the plans and an entrance sidelight has been installed by mistake! Hopefully these errors are easily rectifiable and won't cause much delay in proceeding to the next stage.






We also noticed that the water piping looks like it has only been dug 15cm into the ground and are concerned that this might become a potential problem when we do the landscaping/driveway. We are afraid that the landscapers might have to rip everything out if the pipes get in the way of the digging and re-lay them again, all of which will add to the cost. Anyway, to be safe, we will check with our Site Supervisor if connections can be run along the side of the house instead of the front.



Wednesday 1 August 2012

Frames are up!

1 AUGUST 2012